Epoxy Installation

  Day 1      
    
Door taped to keep dust out of home
 
    
Floor prepped with sanders & blades
 

Hand grinding bad areas
 
 
 
Cracks filled and hand ground
 

Stem walls prepped

Stem walls first to be coated & chipped
 
 
Coating starts

Continues.  Takes 2-5 layers to cover

After  coating, chips cast into epoxy
 
 
                       

 

 

 


Day 2  
Epoxy needs a day to harden before applying the top coat
 

Day 3   Installer arrives, cleans garage, driveway and top coats with a high grade urethane.

After the top coat, please stay off the floor for three days.  After that: boxes, bicycles, etc. can be brought back into the garage.  But please be careful.  The urethane takes 7 days to completely cure.  If you have heavy objects with a small foot-pattern like refrigerators and tool boxes with wheels, keep off for 7 days along with your car or truck.

 